Published in the Journal officiel on 24 July 2026, theorder of 20 July 2026 sets out how Article 175 of the 2025 Finance Act is to be implemented: solar and onshore wind installations benefiting from a feed-in tariff or a contract for difference will have to stop generating during negative-price episodes, at the request of their counterparty.
A two-step timeline
- Until now : only installations above 10 MW were affected.
- From 1 December 2026 : the threshold falls to 5 MWp for solar and 5 MW for onshore wind.
- From 1 March 2027 : installations of 1 to 5 MW are also brought into the scheme.
In practice, the offtaker, most often EDF OA, sends a binary instruction: normal operation or complete shutdown. Any electricity exported during a requested shutdown is not paid for under the contract.
Flat-rate compensation
Shutdown hours are compensated on a flat-rate basis, calculated from installed capacity, the contract tariff, the duration of the shutdown and a load factor set at 0.47 for solar and 0.25 for onshore wind. Payments are monthly, with an annual true-up.
A growing phenomenon
According to RTE, France recorded 407 hours of negative prices in the first half of 2026, compared with 513 hours over the whole of 2025 and 147 hours in 2023. These episodes last five hours on average and are concentrated between 11 am and 4 pm, right at the peak of solar generation.
What this means for valuation
- A new parameter in business plans : the expected number of shutdown hours and the actual level of compensation must be modelled asset by asset.
- A gap depending on the generation profile : for a plant whose actual midday output exceeds the flat-rate factor, compensation may be lower than the revenue lost.
- A case for storage : adding a battery to an existing plant makes it possible to shift exports to higher-value hours.
Almavision's view
For contracted assets of 1 to 10 MW, curtailment during negative prices is no longer a theoretical risk: it is an operating parameter to document before any sale. Buyers will now ask for an hourly production history and an estimate of shutdown hours; better to prepare them upfront.
Planning a sale, an acquisition or a valuation?
Let's talk: we will get back to you quickly.
Contact us →