Market analysis

Battery storage in France: a market scaling up

Long confined to a handful of demonstrators, battery storage (BESS) has become a fully fledged segment of the energy transition in France. According to RTE's 2025 electricity report, 1.6 GW of batteries were in operation at the end of 2025, and around 14 GW of projects were in the grid connection queue.

The need for flexibility is very real: in 2025, around 3 TWh of solar and wind output was not generated during negative-price episodes, almost twice as much as in 2024. Solar curtailment alone reached 1.6 TWh. That is energy a well-located storage asset can help monetise.

Projects scaling up

  • Sharply rising unit capacities : 240 MW / 480 MWh in Cernay (TAG Energy), 120 MW / 240 MWh in Saleux (Kallista Energy), 100 MW / 200 MWh already in operation for Harmony Energy.
  • Longer durations : the existing fleet has an average duration of around 1.1 hours, but recent projects target nearly 2 hours.
  • New entrants alongside the pioneer NW (around 950 MW in operation): Alpiq, Eni, Q Energy, TAG Energy, Acacia…
  • Ambitious prospects : Modo Energy expects around 5 GW of batteries in France by 2030.

A segment in high demand among investors

Across Europe, storage is one of the few growing segments of the transaction market. In the first quarter of 2026, battery deal volume rose by around 120% year on year to nearly 5.5 GW across 26 transactions, while solar and wind volumes fell by 20 to 30%. Ready-to-build projects are emerging as buyers' preferred entry point.

Three project models

  • Standalone storage, connected near a substation, monetising ancillary services and market arbitrage.
  • Co-location with a solar plant, sharing the grid connection point and reducing CAPEX, but dependent on the space available at the delivery substation and on the power limits set by the grid operator.
  • Behind-the-meter storage, at an industrial site or coupled with a self-consumption installation: according to Enedis, around 16% of solar installations connected in the second quarter of 2026 were fitted with a battery.

Key valuation watch-points

  • Grid connection remains the main bottleneck, especially for high-voltage projects.
  • Changing revenues : early projects captured short-term ancillary services; their future profitability will depend more on arbitrage and the ability to stack several revenue streams.
  • Critical size : an asset of a few MW can be monetised through ancillary services, whereas a very small asset will need to go through an aggregator.
  • Cell prices and the customs context, which weigh directly on CAPEX.

Almavision's view

Storage now attracts a wide range of investors, from utilities to infrastructure funds. To sell or finance a battery project at the right price, three things must be demonstrated: a secured grid connection, a diversified and documented revenue model, and a long-term value strategy (duration, degradation, augmentation). This is where the difference lies between an "interesting" project and a truly bankable one.