Regulation

S21 tariffs: the French State wants to revise 300–500 kWp solar contracts

Until now, successive reforms of the "S21" tariff order only targeted new projects. The 2027 Finance Bill, tabled on 1 October 2026 in the National Assembly, crosses a threshold: its Article 82 provides for a downward revision of the feed-in tariff of contracts already signed, for solar installations on buildings, sheds or carports of 300 to 500 kWp.

Update (22 October 2026): Article 82 has been deleted by the Economic Affairs Committee and then by the Finance Committee. Read our article on these votes and the next steps.

S21 already tightened for new projects

Created by the order of 6 October 2021, S21 governs support for building-mounted installations up to 500 kWp. It has been overhauled in two stages:

  • March 2025 : the 100–500 kWp segment leaves the open window for a simplified tender. The tariff for this segment had fallen from €131.2/MWh in 2023 to €114.1/MWh in 2024, then to €95/MWh. The latest round of the "small PV" tender came out at around €75/MWh.
  • June 2026 : the order of 1 June 2026 (complete grid connection requests filed from 5 June) introduces a single tariff of €11/MWh for electricity exported by installations of up to 100 kWp, compared with €40–47/MWh previously for surplus power. This tariff is indexed at 2% per year, i.e. around €16/MWh in year 20. The investment premium is abolished. Self-consumption becomes the reference model.

What Article 82 of the 2027 Finance Bill provides

  • Scope : contracts concluded under the S21 order for installations of at least 300 kWp and less than 500 kWp in mainland France. According to Enerplan, around 8,000 installations are affected, mainly on farm buildings, local authority facilities and SME premises.
  • The mechanism : the cut would vary according to location, yield, commissioning date, operating conditions and the technical characteristics of the installation. It would also rely on a sector-wide CRE audit of costs and return on capital. The reduction levels and their effective dates would be set by a later order, after consulting the CRE.
  • Order of magnitude : the ministry mentions a target tariff of around €92/MWh, compared with an observed average of around €110/MWh on these contracts. Expected savings are estimated at around €120 million in 2027.
  • A safeguard clause : a producer whose viability is threatened could obtain different terms. A major point of attention: according to the text, this remedy would not be available to producers that change their shareholding or financing after 1 October 2026.

Other measures in the bill

  • 2006 and 2010 contracts : installations above 250 kWp under the 2006 and 2010 tariff orders, some of which earn up to €600/MWh, would see their contracts terminated early, at a date guaranteeing a "reasonable return on capital".
  • Negative prices : the obligation to stop generating during negative-price hours would be extended to installations above 100 kW by the end of 2027 at the latest, after thresholds of 5 MW on 1 December 2026 and 1 MW on 1 March 2027. This is no marginal issue: 513 hours of negative prices were recorded in 2025, and around 300 in the first half of 2026 alone.
  • Early terminations : contracts deemed costly for the State could be terminated more easily, notably for small installations of up to 36 kWp.

A highly contested measure

Enerplan is calling for the provision to be withdrawn. The trade association points out that the tariffs were set by the State itself, that their level reflects the indexation provided for in the order during a period of inflation, and that in 2022, when market prices exceeded the tariffs, these installations reduced public energy service charges. Its president, Daniel Bour, stresses that a sector representing jobs and businesses cannot be used as a budgetary adjustment variable. Failing withdrawal, the industry is asking for the audit method to be published beforehand and for projects that remain within the order's profitability parameters to be excluded.

Legally, calling into question contracts signed less than five years ago is a major break. Specialist lawyers expect significant litigation. In 2023, the Conseil d'État annulled the order revising the 2006–2010 contracts, while upholding the principle of the mechanism. The bill is still to be debated in Parliament this autumn and may change.

What this means for sales and acquisitions

  • A risk to factor into models : for any 300–500 kWp asset under an S21 contract, buyers will assume a revised tariff scenario (around €92/MWh) and apply a discount until the final levels are known.
  • Transaction timing : if the restriction on the safeguard clause is confirmed, a sale or refinancing completed after 1 October 2026 could deprive the producer of this remedy. Each ongoing transaction must be analysed case by case.
  • Contractual mechanisms to plan for : earn-outs linked to the final tariff, specific warranties, conditions precedent tied to the publication of the implementing order.
  • More detailed due diligence : commissioning date, actual yield, CAPEX actually incurred and financing structure become the parameters that will determine the size of the cut, and therefore the value.

Almavision's view

Beyond its budgetary impact, this measure undermines confidence in the State's signature, which is the foundation of the value of assets under feed-in contracts. For owners of 300–500 kWp installations, the immediate priority is to document each project's actual profitability (costs, financing, yield) so as to be ready for the CRE audit, and to secure the timing and structure of any ongoing transaction. For buyers, the market could open up opportunities at discounted prices, provided the regulatory risk is closely managed.

Sources