Regulation

S21 order of 1 June 2026: a single €11/MWh tariff for small-scale solar

The order of 1 June 2026, published in the Journal officiel on 4 June, overhauls the "S21" tariff order of 6 October 2021 for solar installations on buildings, sheds or carports of up to 100 kWp. It applies to complete grid connection requests filed from 5 June 2026.

What changes

  • A single tariff of €11/MWh (1.1 c€/kWh) for exported electricity, indexed at 2% per year, compared with €40–47/MWh previously for surplus sales.
  • The removal of the investment premium, which until now supported self-consumption installations.
  • Priority given to self-consumption : the business model now relies on electricity consumed on site, with exports merely a top-up.
  • Simplified procedures, with a single process for the purchase contract application and the grid connection request.

Projects whose complete grid connection request was filed, or whose contract was signed, before 5 June keep the previous terms.

Why this reform

After the 100–500 kWp segment moved to a simplified tender in 2025, applications shifted massively to the 9–100 kWp segment: 291 MW in the third quarter of 2025, against a target of 92.25 MW. In its favourable opinion, the CRE also noted that 70 to 80% of applications in the 36–100 kW segment were for full export. The stated aim is to slow down the open window and refocus support on self-consumption, at a near-neutral cost to public finances.

What this means for the market

  • A "full export" model that is no longer profitable on small and mid-size rooftops: value is shifting to projects backed by on-site consumption.
  • Scarcity of projects under the old regime : installations connected or secured before 5 June become more attractive.
  • A new role for third-party investors and integrated offers (generation, consumption, storage) for businesses.

Almavision's view

For owners of rooftop portfolios, the filing date of the grid connection request becomes a key value driver. In a sale, it must be documented project by project, just like the purchase contract and the site's consumption profile.

Sources

Planning a sale, an acquisition or a valuation?

Let's talk: we will get back to you quickly.

Contact us →
Share:LinkedInEmail