Since the March 2025 reform, rooftop solar installations of 100 to 500 kWp no longer fall under the open-window feed-in tariff but under a simplified tender. The results of its first round, which closed on 2 October 2025, show a hesitant start.
Key figures
- Volume on offer : 192 MWp.
- Volume submitted : 291 bids for 82.1 MWp, around 43% of the volume on offer.
- Volume awarded : 157 bids for 43.5 MWp.
- Weighted average price of winning bids : €88.73/MWh, against a price cap of €95/MWh.
- Breakdown : 129 rooftop projects, 22 carport projects and 6 mixed projects selected.
Nearly one bid in three was rejected as non-compliant, most often because of a guarantee still referring to the former S21 scheme.
Lessons learned
- A transition that takes time : moving from an open window to a tender imposes new constraints on developers (guarantees, timing, competition) that many had not yet taken on board.
- A premium for self-consumption : individual or collective self-consumption projects were selected at lower prices (€82.73 and €86.86/MWh) than full-export projects (€90.73/MWh).
- Adjustments expected : the CRE recommends giving more visibility on the 2026 calendar, concentrating volumes on fewer rounds and helping bidders with the causes of non-compliance.
Almavision's view
This first result confirms that the mid-size rooftop segment is becoming selective. For a developer, the administrative rigour of the bid becomes a success factor in its own right. For a buyer, projects awarded in these first rounds, at a price close to €89/MWh, are well-positioned assets.